Commercial Projects

Picture of Microsoft

Bellevue Place Expansion Hyatt Regency Hotel, Bellevue, WA
Completed: June 2009

$185 million hotel transformation includes a second tower addition, auditorium, expansion to 733 guest rooms and over 60,000 square feet of meeting and event space. Inspections include reinforced concrete, post tension concrete, epoxy grouted anchors, structural steel erection, fireproofing, and masonry.

Picture of Microsoft

Ziba World Headquarters, Portland, OR
March 2008 - Present

New 700,000 square foot building designed for LEED Gold Certification, with office and ground-level retail space. Inspections include reinforced concrete, grout driven pile concrete, baseplate grout, epoxy grouted anchor, expansion anchor, structural steel fabrication and erection, and cold form steel framing.

Picture of Microsoft

City Center Plaza, Bellevue, WA
Completed: August 2008

$80 million, 571,000 square foot, 26-story office tower with 1,483 below grade parking spaces. Inspections include shoring, reinforced concrete, batchplant, shotcrete, fireproofing and structural steel erection.

Picture of Microsoft

Microsoft West Campus Expansion, Redmond, WA
June 2007 - June 2009

Campus expansion including a new parking garage, storm vaults and five new buildings. Inspections include reinforced concrete, post tension concrete, epoxy grouted anchors, expansion anchors, masonry, structural steel fabrication and erection, ultrasonic testing and fireproofing.

Picture of Washington Mutual Tower

Washington Mutual Tower, Seattle, WA
Completed: March 2006

$140 million new tower consisting of a 42-story office building, 16-story museum building and 5 level, 700 stall underground parking garage. Project has steel frame construction with concrete core for seismic resistance. Inspections include shoring, reinforced concrete, masonry, fireproofing, structural steel fabrication and erection, shotcrete, ultrasonic testing and floor flatness testing. Large 10,000 yard MAT pour with 6 pump trucks required round the clock inspection and ultilized over 20 inspectors. Performed structural steel fabrication shop audits at Canron in Portland and British Columbia.

Picture of Rivergate

Rivergate Corporate Center Phase II, Portland, OR
Completed: December 2004

607,000 square foot concrete tiltup building part of large industrial development project. Inspections include reinforced concrete, floor flatness testing, structural steel fabrication and erection, diaphragm nailing, epoxy/expansion anchors, ultrasonic testing and fireproofing.

Picture of Skinner Building

Skinner Building Seismic Upgrade, Seattle, WA
Completed: August 2004

Seismic upgrade to existing office building. Inspections include reinforced concrete, epoxy grouted anchors, structural steel, wood framing and fireproofing.

Picture of Amgen Headquarters

Amgen Headquarters, Seattle, WA
Completed: March 2004

$400 million, 29 acre, new headquarters for biotechnical corporation. Project includes 8 buildings for offices, laboratories, fitness center, conference facility, library and utility plant. Onsite office and laboratory provided. Inspections include soils density, cast-in-place, post tension and precast concrete, structural steel fabrication and erection, ultrasonic testing, concrete, masonry, wood framing and asphalt density. Performed shop inspections for structural steel and precast concrete.